Korea Electric Power Company handles nation-wide electrical issues.
| Demand charge (won/household) | Energy charge (won/kWh) | ||
|---|---|---|---|
| 1~100kWh | 370 | 1~100kWh | 55.10 |
| 101~200kWh | 820 | 101~200kWh | 113.80 |
| 201~300kWh | 1,430 | 201~300kWh | 168.30 |
| 301~400kWh | 3,420 | 301~400kWh | 248.60 |
| 401~500kWh | 6,410 | 401~500kWh | 366.40 |
| 501kWh~ | 11,750 | 501kWh~ | 643.90 |
| Demand charge (won/household) | Energy charge (won/kWh) | ||
|---|---|---|---|
| 1~100kWh | 370 | 1~100kWh | 52.40 |
| 101~200kWh | 670 | 101~200kWh | 89.30 |
| 201~300kWh | 1,150 | 201~300kWh | 132.50 |
| 301~400kWh | 2,830 | 301~400kWh | 192.50 |
| 401~500kWh | 5,360 | 401~500kWh | 288.90 |
| 501kWh~ | 9,770 | 501kWh~ | 521.70 |
For service starts or expansions, select a company with a valid electric work license and let them perform indoor wiring work first. File the relevant application at any KEPCO branch office and prepare the necessary documents.
1. Methods of Applying
2. Required Documents
Electric Rates Table
| Less than 5kW (residential etc) |
* Service start application form (I) (from KEPCO) * No documents required; submit a copy of a valid ID card or building management ledger if necessary. In case of lessee applicants, have the owner sign below the name of the electricity user and submit a copy of the lease contract. |
|---|---|
| More than 6kW of contract power |
* Service start application form (II) (from KEPCO) Apply by visiting a KEPCO branch office or through the KEPCO Cyber Branch Office or by Call Center (☎123).Customer with contract power of 5kW or less can apply for use of electricity without presenting any documents.When applying under a name other than one’s own, the customer’s payment of electric charge should be guaranteed.2. Required documents (more than 6kW of contract power)Electricity Use Application Form (II) Building Register or Land Register Copy of owner’s ID card (or Resident Registration), Corporate Seal Registration Certificate(for corporation), or copy of lease contract (when applying under the name of lessee) C28 Copy of user’s ID card (or Resident Registration) or Corporate Registration Certificate(for corporation) Copy of business registration certificate (for individual) 31:31 The user’s electric charge payment shall be guaranteed by paying the deposit, if necessary. C29″ |
In case KEPCO performs the inspection prior to use, submit the application for inspection prior to use and the single line diagram (indoor wiring drawing) together with the electricity use application three days before the preferred inspection date. A copy of the business registration certificate and the certificate of completion of inspection prior to use should be submitted before using electricity. You may also present a copy of your ID card or business registration certificate of the other place using electricity (when relocating the business). Business registration certificates should be submitted immediately upon issuance, however.
Agricultural Well (groundwater): Submit the groundwater development report (certificate) from the mayor or the governor and the land ledger.
In case of reapplication after canceling the existing electricity use application, submit a new electricity use application form in case that there is no change.
3. Construction Cost
For the electricity use application, the standard construction cost is generally applied except in for special cases (note that this is different from the indoor wiring work cost paid to the installers).
4. Beginning of Service
Source: http://www.kepco.co.kr/eng/ .